《监理竣工验收程序.pdf》由会员分享,可在线阅读,更多相关《监理竣工验收程序.pdf(8页珍藏版)》请在taowenge.com淘文阁网|工程机械CAD图纸|机械工程制图|CAD装配图下载|SolidWorks_CaTia_CAD_UG_PROE_设计图分享下载上搜索。
1、监理竣工验收程序 is not less than 3 metres in length,not less than 1 m on both sides,Derrick(gantry)ceiling heights of more than 30 meters double.(2)the Derrick(gantry)ground floor entrance has ever,and floor openings with safety doors,both sides of the channel set fence,under the skirting.(3)the Derrick(ga
2、ntry)falls within the basket installed doors,the height limit,rope,safety devices such as floor stop.(4)the Derrick(gantry)provided 监理竣工验收程序、评估和内容 建设部发布的建建2000142 号文房屋建筑工程和市政基础设施工程竣工验收暂行规定(以下简称暂行规定)及建设部令第 78 号房屋建筑工程和市政基础设施工程竣工验收备案管理暂行办法(以下简称暂行办法)已颁布执行一年了,建设工程竣工验收由核验制改革为备案制,沿用多年的由建设工程质量监督机构对竣工验收的工程进行
3、质量等级核定改为由建设单位组织参建单位和有关专家组成验收组对竣工工程进行检查验收,通过办理备案手续得到确认。但在实际竣工验收过程中,有些监理工程师还不了解竣工验收的程序和内容,不熟悉暂行规定及暂行办法,不清楚监理单位要做的工作以及要求监理单位提供的质量评估报告的内容。所以,本文对竣工验收的程序和内容,竣工验收阶段监理工程师应做的工作及质量评估报告的内容进行了归纳及总结。可供同行参考。1、竣工验收阶段监理单位的本职工作 1.1 审核承包单位报送的工程技术资料,并对工程质量进行竣工预验收。1.2 对工程质量进行评估,提出工程质量评估报告。并在承包单位提交的工程竣工报告及工程竣工报验单上签署监理意见
4、。1.3 参加由建设单位组织的竣工验收。1.4 在竣工验收会议上,汇报监理合同履约情况及工程质量情况。1.5 接受有关方面对监理档案资料的审查。is not less than 3 metres in length,not less than 1 m on both sides,Derrick(gantry)ceiling heights of more than 30 meters double.(2)the Derrick(gantry)ground floor entrance has ever,and floor openings with safety doors,both side
5、s of the channel set fence,under the skirting.(3)the Derrick(gantry)falls within the basket installed doors,the height limit,rope,safety devices such as floor stop.(4)the Derrick(gantry)provided is not less than 3 metres in length,not less than 1 m on both sides,Derrick(gantry)ceiling heights of mor
6、e than 30 meters double.(2)the Derrick(gantry)ground floor entrance has ever,and floor openings with safety doors,both sides of the channel set fence,under the skirting.(3)the Derrick(gantry)falls within the basket installed doors,the height limit,rope,safety devices such as floor stop.(4)the Derric
7、k(gantry)provided 1.6 在验收各方人员共同签署的竣工验收报告及竣工验收备案表上签字。2、竣工验收阶段协助建设单位的工作 2.1 就竣工验收的程序和内容向建设单位提出建议及咨询,协助建设单位制订竣工验收方案、确定验收组成员名单及竣工验收程序。2.2 协助取得城乡规划、公安消防、环保等部门的认可文件或准用文件。2.3 协助通知当地建设工程质量监督机构。2.4 协助组织竣工验收。2.5 记录、归纳建设、勘察、设计、施工、监理等参与各方的工程合同履约情况和执行法律、法规和标准等情况的汇总材料。2.6 协助审阅上述各参与方的工程档案资料。2.7 协助组织实地工程质量查验。2.8 协助
8、建设单位对工程勘察、设计、施工、设备安装质量和管理环节等方面作出全面评价,协调各方意见,起草竣工验收意见。2.9 协助建设单位向当地建设行政主管部门报送竣工验收备案文件。3、竣工验收程序 3.1 竣工预验收 3.1.1 当单位工程达到竣工验收条件时,承包单位应在自审、自查、自评工作完成后,填写工程竣工报验单,并将全部竣工验收资料(质量保证资料、评定资料、施工技术资料、施工管理资料、竣工图)报 is not less than 3 metres in length,not less than 1 m on both sides,Derrick(gantry)ceiling heights of
9、more than 30 meters double.(2)the Derrick(gantry)ground floor entrance has ever,and floor openings with safety doors,both sides of the channel set fence,under the skirting.(3)the Derrick(gantry)falls within the basket installed doors,the height limit,rope,safety devices such as floor stop.(4)the Der
10、rick(gantry)provided 送项目监理部,申请竣工验收。3.1.2 总监理工程师组织各专业监理工程师对竣工资料及各专业工程的质量情况进行全面检查,对检查出来的问题,应督促承包单位及时整改。3.1.3 验收合格后,由总监理工程师签署工程竣工报验单,并向建设单位提出质量评估报告。3.2 竣工验收 监理单位参加由建设单位组织的竣工验收。3.2.1 建设单位、勘察单位、设计单位、施工单位、监理单位分别书面汇报工程建设项目质量状况、工程合同履约情况以及执行国家法律、法规和工程建设强制性标准情况。3.2.2 检查工程建设参与各方提供的竣工资料。3.2.3 检查工程实体质量。根据工程具体情况,
11、对建筑工程的使用功能进行抽查检验。3.2.4 对竣工验收情况进行汇总讨论,形成竣工验收意见,填写建设工程竣工验收备案表、建设工程竣工验收报告。3.3 竣工验收备案 建设工程竣工验收完毕以后,由建设单位负责,在 15 天范围内向备案部门办理竣工验收备案。4、质量评估报告的主要内容 工程质量评估报告是监理工程师对工程质量客观、真实的评价,是工程竣工验收时监理单位必须提交的资料。质量评估报告应随工程 is not less than 3 metres in length,not less than 1 m on both sides,Derrick(gantry)ceiling heights of
12、 more than 30 meters double.(2)the Derrick(gantry)ground floor entrance has ever,and floor openings with safety doors,both sides of the channel set fence,under the skirting.(3)the Derrick(gantry)falls within the basket installed doors,the height limit,rope,safety devices such as floor stop.(4)the De
13、rrick(gantry)provided is not less than 3 metres in length,not less than 1 m on both sides,Derrick(gantry)ceiling heights of more than 30 meters double.(2)the Derrick(gantry)ground floor entrance has ever,and floor openings with safety doors,both sides of the channel set fence,under the skirting.(3)t
14、he Derrick(gantry)falls within the basket installed doors,the height limit,rope,safety devices such as floor stop.(4)the Derrick(gantry)provided 进展阶段编写,目前通常编写地基与基础分部工程、主体分部工程及单位工程质量评估报告。工程质量评估报告的主要内容有:4.1 工程慨况 4.1.1 建设地点。4.1.2 建筑面积。4.1.3 层数。4.1.4 建筑使用功能。4.1.5 结构形式(地基处理方案,基础及主体结构形式),抗震设防烈度,结构抗震等级。4.1
15、.6 建筑装饰特色。4.1.7 水、暖、电、通风、空调等设备安装工程的特点。4.1.8 建设单位、勘察单位、设计单位、施工单位和监理单位名称。4.2 项目监理机构组织 项目监理机构人员组织名单。注册监理工程师岗位证书编号。4.3 质量评估依据 4.3.1 设计图纸 4.3.2 施工承包合同 4.3.3 工程建设标准强制性条文房屋建筑部分 4.3.4 现行建筑安装工程质量检验评定标准 4.3.5 施工验收规范 4.3.6 国家、地方有关建设工程质量管理法规。4.4 工程质量概况 is not less than 3 metres in length,not less than 1 m on bo
16、th sides,Derrick(gantry)ceiling heights of more than 30 meters double.(2)the Derrick(gantry)ground floor entrance has ever,and floor openings with safety doors,both sides of the channel set fence,under the skirting.(3)the Derrick(gantry)falls within the basket installed doors,the height limit,rope,s
17、afety devices such as floor stop.(4)the Derrick(gantry)provided 4.4.1 概述工程建设情况,重点说明地基验槽、地基与基础验收、人工地基或桩基检测、主体验收、竣工初步验收等情况:4.4.2 施工过程中有无质量事故及质量事故处理情况:4.4.3 建筑沉降观测情况。4.4.4 建筑主要使用功能情况。4.4.5 设备调试、试运转情况。4.5 质量等级评定情况 每个分项工程完成后,监理工程师应在承包单位自评自核的基础上,通过讨论保证项目、基本项目、允许偏差项目核查,确认分项工程的质量等级。4.5.1 单位工程的组成划分。4.5.2 各分部
18、工程质量等级的核定。4.5.3 单位工程的综合评定。4.6 质量评估意见 对于达到竣工验收要求的工程,质量评估意见通常有以下内容:4.6.1 完成工程设计和合同约定的各项内容。4.6.2 工程资料完整有效。4.6.3 完成的工程质量符合有关法律、法规和工程建设强制性标准,符合设计要求和合同要求。4.6.4 质量等级优良或合格。4.6.5 符合竣工验收备案要求。4.6.6 同意竣工验收。is not less than 3 metres in length,not less than 1 m on both sides,Derrick(gantry)ceiling heights of more
19、 than 30 meters double.(2)the Derrick(gantry)ground floor entrance has ever,and floor openings with safety doors,both sides of the channel set fence,under the skirting.(3)the Derrick(gantry)falls within the basket installed doors,the height limit,rope,safety devices such as floor stop.(4)the Derrick
20、(gantry)provided is not less than 3 metres in length,not less than 1 m on both sides,Derrick(gantry)ceiling heights of more than 30 meters double.(2)the Derrick(gantry)ground floor entrance has ever,and floor openings with safety doors,both sides of the channel set fence,under the skirting.(3)the De
21、rrick(gantry)falls within the basket installed doors,the height limit,rope,safety devices such as floor stop.(4)the Derrick(gantry)provided 最后,项目总监理工程师及监理单位技术负责人签字盖章。5、结语 房屋建筑工程竣工验收是工程建设的最后一个程序,是全面检验工程建设是否符合设计要求的重要环节,是监理工程师的一项重要工作。尤其是在许多建设单位不熟悉竣工验收程序情况下,监理工程师必须明确自身职责,按暂行规定、暂行办法及建设工程监理规范中确定的内容和程序做好本职工作,并积极协助建设单位做好相应的工作。(摘自2003 年第 2 期)