1、Four short words sum up what has lifted most successful individuals above the crowd: a little bit more.-author-datePrince 2 题库Prince 2 题库601道题目随机考75道,皆为单选题,难度比较大,要认真复习。一定不要给外国人知道,不要互相传阅,谨防哪个傻逼告诉外国人。学长 祝学弟学妹们顺利毕业,个个都是Merit1. Which of the following is a characteristic of project work? BA. Projects hav

2、e a permanent natureB. Projects require people with various and different skillsC. Projects repeat the same work over and overD. Projects remove all uncertainty from the work2. Which of the following is a characteristic of project work? DA. Each project is the same as the previous oneB. Projects do

3、not need to end at all C. Every project uses the same team of peopleD. Projects introduce change3. Which of the following is a characteristic of project work? AA. Projects are temporary in natureB. Projects can only be undertaken when there are no known risksC. Every project must have the same suppl

4、ierD. Projects and business as usually are the same discipline4. Which of the following is a characteristic of project work? CA. Projects remove all uncertainty from the workB. Projects are permanent undertakingsC. Projects introduce changeD. Projects solve every business problem5. Which of the foll

5、owing does project management wish to control? BA. People B. CostsC. ProfitD. Space6. Which of the following does project management wish to control? CA. TimekeepingB. AbsenteeismC. BenefitsD. The day job7. Which of the following does project management wish to control? DA. Risk and PeopleB. Quality

6、 and QuantityC. Work practices and ScopeD. Costs and Timescales8. Which of the following does project management wish to control? CA. Business as usualB. The original idea for the productC. Risk and ScopeD. Long term product use9. Which of the following is true for PRINCE2 ? CA. It can only be used

7、on certain types of projectB. It is specific to certain industriesC. It can be applied to any projectD. It concentrated on the Specialist techniques used b developers10. Why does PRINCE 2 suggest that a study to investigate the situation and determine options for the way ahead be run as a separate p

8、roject? AA. Each option would have a different Project Plan, Business Case and set of risksB. It would over-complicate the projectC. PRINCE 2 cannot handle multiple optionsD. A feasibility study cannot be part of a programme11. Which of the following statements is FALSE? CA. Embodies best practice a

9、nd governanceB. Is based on management by exceptionC. requires fixed progress meetingsD. promotes consistency of project work12. Which of the following statements is TRUE? PRINCE 2 provides which of the following? AA. A project management methodB. A programme management methodC. Line management tech

10、niquesD. All of the above13. Which of the following statements is FALSE? AA. Fixed progress meetingsB. Delegation of authorityC. Dividing the project into management stagesD. Time event driven progress reporting14. Which of the following statements is FALSE?PRINCE 2 provides projects with DA. good c

11、ommunication channels between project management and the rest of the organisationB. regular reviews of progress against the Business CaseC. flexible decision pointsD. complete absence of deviations15. In PRINCE 2 what is the name of the product that is used to define the information that justifies t

12、he setting up, continuation or termination of the Project? AA. The Business CaseB. The End Stage ApprovalC. The Project BriefD. The Project Mandate16. In PRINCE 2 what answers the question: Why should this project be done? AA. The Business CaseB. The End Stage ApprovalC. The Project BriefD. The Proj

13、ect Mandate17. Which one of these is NOT a PRINCE 2 Theme CA. OrganisationB. QualityC. Product-based planningD. Progress18. Which one of these is NOT a PRINCE 2 Theme? BA. RiskB. Quality ReviewC. PlansD. Change19. Which one of these is a PRINCE 2 Theme? AA. Risk B. Quality ReviewC. Product-base plan

14、ningD. Product Descriptions20. Which one of these is NOT a PRINCE 2 These? DA. RiskB. QualityC. ProgressD. Directing a Project21. Which of these statements is FALSE? AA. A PRINCE 2 plan is based on Work Breakdown StructureB. A PRINCE 2 plan is kept in line with the Business CaseC. A PRINCE 2 plan ne

15、eds approvalD. A PRINCE 2 plan is more than a bar chart showing timescales22. Which of the following is a reason for tailoring PRINCE 2? CA. Ensuring that the method is related to the projects environmentB. Ensuring the projects control is based on the projects scaleC. Both of the aboveD. None of th

16、e above23. Which of the following provides the vital test of the viability of a project? BA. The Project FileB. The Business CaseC. Application of specialized techniquesD. Technical Stages24. What environment does PRINCE 2 assume? BA. A fixed-price contractB. A Customer/supplier environmentC. A spec

17、ialist environmentD. A third-party environment25. What is defined as: the result of the change derived from using the outputs? BA. ItemsB. OutcomeC. ProductD. Theme26. Complete the following phraseA project is a temporary organization that is created for the purpose of delivering one or more busines

18、s products according to DA. The customers needsB. an agreed contractC. the Project PlanD. an agreed Business Case27. A project is a temporary organization that is created for the purpose of delivering one or more CA. ActivitiesB. StagesC. Business productsD. Techniques28. Completed the following phr

19、aseA project is temporary organization that is created for the purpose of delivering one or more_ according to an agreed Business Case. BA. customers needsB. business productsC. componentsD. resources29. What does PRINCE 2 regard as containing the optimum mix of information to judge whether the proj

20、ect is viable within a project? DA. The Risk LogB. The Project Initiation DocumentC. The Project BriefD. The Business Case30. Which concepts does PRINCE 2 use for senior management involvement? BA. Management by acceptanceB. Management by exceptionC. Management by involvementD. Management by consent

21、31. What does PRINCE 2 offer to the Project Board because their project responsibilities are in addition to their normal work? DA. Management accountabilityB. Delegation of accountabilityC. Regular progress meetingsD. Management by exception32. In PRINCE 2 terminology, which phrase is used to descri

22、be an exception? BA. Where there has been a deviation beyond the tolerance levelsB. Where it can be forecast that there will be a deviation beyond the agreed tolerance levlesC. Any major issueD. Where a risk actually occurs33. Which of the following options is detailed in PRINCE 2? CA. People motiva

23、tionB. Earned Value AnalysisC. Product-based planningD. Critical Path Analysis34. Which of the following techniques is part of PRINCE 2? BA. Earned Value AnalysisB. Product-based planningC. Critical Path AnalysisD. Gantt charting35. Which of the following project management aspects is detailed as a

24、theme in PRINCE 2? CA. ContractingB. Earned Value AnalysisC. RiskD. Procurement36. Which of the following options is detailed as a theme in PRINCE 2? BA. Team leadershipB. OrganisationC. Earned Value AnalysisD. Corporate quality management37. How does PRINCE2 provides a firm basis for defining the s

25、cope boundary? CA. By establishing a totally independent Business Case for each projectB. By keeping an independent Risk Log for each projectC. By identifying, defining and analyzing the projects productsD. By defining the Business/User/Supplier roles38. The PRINCE 2 approach to project management i

26、s: AA. Process-basedB. Component-basedC. Technique-basedD. Control-based39. Which of the following statements is/are correct? C1. PRINCE 2 is suitable for both small and large projects2. PRINCE 2 can be applied regardless of the industry or field of workA. Only the firstB. Only the secondC. BothD. N

27、either40. Consider the assertions given below: are the assertions true? B1. As a project management method, PRINCE 2 is also suitable for programme management2. The PRINCE 2 method is not dependent on the area of applicationA. Only the first assertion is trueB. Only the second assertion is trueC. Bo

28、th are trueD. Neither are true41. Which of the following three statements are true of a PRINCE 2 project? D1. There is no standard approach to a project2. Activities down to the level of Work Package are identified during Project Initiation3. A project is a temporary structureA. Only 1 and 2B. Only

29、1C. 1, 2 and 3D. Only 342. PRINCE 2 assumes a Customer/Supplier environment and is written from which standpoint? AA. These two parties/may or may not be part of the same organisationB. These two parties will share common senor managementC. The two parties will share the same business caseD. The two

30、 parties must come from commercially separate organisations43. Which of the following statements is/are correct? B1. PRINCE 2 is designed to be used on any type of project2. The way in which PRINCE 2 is applied to each project must be the same3. Tailoring the method to suit the circumstances of a pa

31、rticular project is critical to its successful use.A. Only the first twoB. Only the first and thirdC. All of themD. Only second and third44. Which of the following statement is/are correct? C1. PRINCE 2 is designed to be used on any type of project in any environment2. The way in which PRINCE 2 is a

32、pplied to each project cannot vary3. Enforcing the method in spite of the circumstances of a particular project is critical to its successful useA. Only the first twoB. Only the first and thirdC. Only the first oneD. Only the second and third45. Which role from the following list does PRINCE2 say ca

33、n be delegated? BA. Project ManagerB. Project AssuranceC. ExecutiveD. Senior User46. Which role is there to ensure that proposals for designing and developing the products are realistic? AA. Senior SupplierB. Senior UserC. Quality AssuranceD. Team Manager47. Which role represents those who will use

34、the product to deliver benefits? BA. Senior SupplierB. Senior UserC. Quality AssuranceD. Team Manager48. monitoring all aspects of the projects performance is a responsibility of which role? DA. Team ManagerB. Configuration LibrarianC. Programme DirectorD. Project Assurance49. On behalf of whom do a

35、ny appointed Project Assurance roles assure the Project? CA. Programme DirectorB. Project ExecutiveC. One or more members of the Project BoardD. Project Manager50. Which of the following phrases are correct? B1. A project normally cross-functional2. A project is likely to required a board base of sk

36、ills for a comparatively short period of time3. A project requires specialist skills to be developed over a long period of time4. Those providing a solution will have different priorities to those with a problem to be solvedA. All are correctB. Only one. Two and four are correctC. Only one, two and

37、three are correctD. Only two and four are correct51. Which individual role is ultimately accountable for the Project? CA. The Project ManagerB. The Senior SupplierC. The ExecutiveD. The Senior User52. Which is a specific responsibility of Project Assurance? BA. Deciding on project issuesB. Checking

38、that the right people are being involvedC. Making project decisions based on the Business Case ManagerD. Reporting highlights to the Project Board53. Which is NOT a possible responsibility of Project Assurance? AA. Deciding on next stage approvalB. Checking that the right people are being involedC.

39、Checking that risks are being controlledD. Constant reassessment of the value-for-money solution54. Which is a possible responsibility of Project Assurance? AA. Checking that the focus on business need is maintainedB. Creation of the Quality Management StrategyC. Giving ad hoc direction to the Proje

40、ct BoardD. Reporting highlights to the Project Board55. Which of the following roles may be assigned to the Project Manager? DA. ExecutiveB. Project AssuranceC. Senior UserD. Team Manager56. The use of which of these plans is OPTIONAL? CA. Project PlansB. Stage PlansC. Team PlansD. All of the above5

41、7. The use of which of the following is mandatory in a PRINCE 2 project? CA. The use of management stagesB. The initiation stageC. Both of the aboveD. Neither (A) not (B) above58. Which does PRINCE 2 regard as the third project interest, given User and Supplier as the other two? CA. TechnicalB. Mana

42、gementC. BusinessD. Quality59. Which does PRINCE 2 regard as the third project interest given Business and Supplier as the other two? BA. ManagementB. UserC. TechnicalD. Quality60. Which does PRINCE 2 regard as the third project interest, given User and Business as the other two? DA. QualityB. Manag

43、ementC. TechnicalD. Supplier61. Which member of the Project Management Team is responsible for the Business Case? AA. The ExecutiveB. The Senior UserC. The Senior SupplierD. The Project Manager62. Who decides on the use of the Project Assurance role? CA. Programme ManagementB. The Project ManagerC.

44、The Project BoardD. Quality Assurance63. If the project needs staff to handle configuration management, they would be part of which group? BA. Project AssuranceB. Project SupportC. Specialist Team D. Programme Directorate64. If the Project needs a configuration librarian, this role would be part of

45、which group? CA. Project AssuranceB. Specialist TeamC. Project SupportD. Programe Directorate65. Which part of the project organisation assists the Project Manager in handling configuration management? BA. Project AssuranceB. Project SupportC. Specialist Team D. Programme Directorate66. If the Proje

46、ct needs staff to handle the use of specific planning and control software, they would be part of which group? DA. Project AssuranceB. Programme DirectorateC. Specialist TeamD. Project Support67. PRINCE 2 assumes that the Project Manager normally comes from: AA. The CustomerB. The SupplierC. An independent consultancyD. The Project Support Office68. Whose responsibility is it